HUD Suspension Stalls WAPA Feeder Rebuild, Transformer Replacements and St. Thomas Battery Project

VIHFA’s October grid report lists four WAPA projects on hold, including plans to replace up to 244 transformers and add devices to isolate faults. The agency says HUD’s suspension blocked three agreements and delayed soil tests for a St. Thomas battery.

  • Ernice Gilbert
  • November 20, 2026
comments
4 Comments
The Randolph Harley Power Plant on St. Thomas in an archival photo. WAPA’s planned rebuild of Feeders 11 and 12 would replace transmission lines between the plant and the Donald Francois Substation.

The Randolph Harley Power Plant on St. Thomas in an archival photo. WAPA’s planned rebuild of Feeders 11 and 12 would replace transmission lines between the plant and the Donald Francois Substation.

Four projects designed to give WAPA more ways to keep power flowing and restore it after faults were on hold as of October, according to the V.I. Housing Finance Authority. The delays include a rebuild of two major feeder lines on St. Thomas, replacement of up to 244 aging transformers across the territory and a battery that would provide backup power to parts of St. Thomas farthest from the Randolph Harley Power Plant.

Advertisement

VIHFA’s October electrical grid report, dated Nov. 2, recorded no expenditures against the $35.79 million budget for its Grid Resiliency program. The broader $67.65 million electrical grid grant, which also covers other initiatives, recorded $1.32 million in spending. The September report also listed all four resiliency projects on hold.

Three of the projects already had authorization to use grant funds, but still needed agreements between VIHFA and WAPA before the utility could solicit bids. VIHFA said it received the agreements from WAPA on July 21, one day after the U.S. Department of Housing and Urban Development’s suspension took effect. The authority said it could not finalize the agreements under the suspension.

The largest of those three projects, the $13.34 million rebuild of Feeders 11 and 12, would replace transmission lines between the Randolph Harley Power Plant and the Donald Francois Substation. The work would give the district a second path for carrying electricity if one line fails. WAPA CEO Karl Knight previously told the governing board that completing the separate Feeder 13 bypass would allow WAPA to move forward with replacing the two lines. VIHFA reported in September that recovery work on Feeder 13 was completed Sept. 13, outside this grant program.

Advertisement

A $1.61 million distribution automation project would add up to 30 devices designed to isolate faults so crews can restore service faster to unaffected parts of the grid. A $3.21 million transformer project would replace up to 244 degraded units serving residential customers territorywide. Both figures include administrative costs.

The $17.39 million East End battery project faces another set of hurdles. The proposed 15-megawatt, 30-megawatt-hour system would provide backup power on Feeders 7C and 9C. VIHFA said it could not hire a laboratory to test soil at the site during the suspension. It was also awaiting a determination from the Department of Planning and Natural Resources that the project is consistent with coastal management requirements. Without those steps, the authority said it could not complete the environmental review and request release of the grant funds.

Advertisement

In July, Mr. Knight told the governing board that WAPA could continue work already authorized but flagged the East End battery as potentially affected. At a Nov. 10 Senate hearing, VIHFA Executive Director Derek Gabriel said the authority’s appeal was ongoing and distinguished work under existing agreements from projects that still need new commitments. The October report gave no start dates for the four grid projects.