Charlotte Amalie Harbor Dredging Expected to Begin by Friday Under $41.9 Million Contract

VIPA says dredging is expected by November 27, after an earlier October target. The $41.9 million contract covers key harbor areas, with material going to St. Croix and the former Cancryn school site during two phases scheduled through October 2027.

  • Staff Consortium
  • November 24, 2026
comments
0 Comments
The tugboat Katan tows marine equipment in a photograph supplied by VIPA. The authority says Charlotte Amalie Harbor dredging is expected to begin by November 27 under a $41.9 million contract.

The tugboat Katan tows marine equipment in a photograph supplied by VIPA. The authority says Charlotte Amalie Harbor dredging is expected to begin by November 27 under a $41.9 million contract. Photo Credit: VIPA.

ST. THOMAS — Dredging of Charlotte Amalie Harbor is expected to begin by Friday, November 27, the V.I. Port Authority announced Tuesday, with equipment already in the territory and preliminary surveys completed for the long-awaited project.

Advertisement

Executive Director Ava Penn said mobilization is underway for work covering the harbor’s entrance channel, turning basin and West Indian Company Limited berthing pocket at Havensight. The project is intended to deepen key areas, improve vessel maneuverability and accommodate the needs of the cruise industry.

The announcement establishes a later start target than VIPA’s September update, which anticipated dredging by October 12. Tuesday’s release did not explain the change. 

Orion Marine Construction is carrying out the work under a contract valued at up to $41,927,000. The VIPA board approved the award in March, and the authority subsequently reported that the agreement was executed June 5, with a 365-day term measured from the start of dredging. 

Advertisement

Operations are planned seven days a week. Work in the main channel and turning basin will take place from sunrise to sunset, while dredging at the WICO berthing pocket and bulkhead will occur overnight.

VIPA said it will coordinate with Orion, WICO, cruise lines and other maritime stakeholders to minimize disruptions and accommodate scheduled ship arrivals and departures. The sequence and timing of work may change because of cruise schedules, weather, marine operations or other project requirements.

The first phase, scheduled from November 2026 through March 2027, will remove material classified as unsuitable for beach use from the entrance channel, turning basin and WICO berthing pocket.

That material will be transported by vessel to the Gordon A. Finch Molasses Pier in Krause Lagoon on St. Croix’s south shore, where it will be temporarily placed for dewatering. Trucks will then move it to a quarry north of Henry E. Rohlsen Airport for final placement.

Preparations for that operation are already underway. Supporting barges arrived on St. Croix November 14 and 15, and crews have begun clearing the temporary stockpile site. VIPA said silt fences were installed last weekend and stabilized site entrances were constructed this week. Preparation of the quarry will follow completion of the temporary stockpile area.

On St. Thomas, the dredge, barges and survey vessel arrived at Crown Bay November 17. A survey conducted November 19 and 20 documented existing harbor conditions to assist with monitoring the work.

The second phase, scheduled from March through October 2027, will remove beach-quality material from the entrance channel. It will be taken by vessel to Crown Bay Cargo Port, unloaded and trucked to the former Addelita Cancryn Junior High School property for storage.

Most of the former school property has been cleared, according to VIPA. Contractor Custom Builders began demolishing buildings there in June. The demolition project cost $2,527,504, funded through a $2 million legislative allocation under Act 9068 and the balance from VIPA’s marine operating revenues.

Advertisement

For the dredging itself, Tuesday’s announcement identified legislative appropriations of $17 million under Act 8787 and $6 million under Act 9068. At the March contract approval, VIPA outlined a plan to fund the remaining $18,927,000 through marine bonds once issued and collected. The latest release did not update the status of that financing. 