Cancer Center Must Recruit Again After Opening Delays Drive Away Hired Staff

Hospital board chair Dr. Jerry Smith says staff hired for the cancer center moved on while awaiting its opening. Equipment purchases exceed $6.99 million, but certification remains pending as lawmakers also question delays in other hospital projects.

  • Nelcia Charlemagne
  • November 25, 2026
comments
0 Comments
Cancer Center Must Recruit Again After Opening Delays Drive Away Hired Staff

ST. THOMAS — Personnel hired to provide critical services at the Charlotte Kimelman Cancer Institute have moved on to other opportunities after delays prevented the facility from opening as anticipated, forcing hospital officials to recruit again while equipment purchases and preparations continue.

Advertisement

Dr. Jerry Smith, chairman of the V.I. Government Hospitals and Health Facilities Corporation board, disclosed the staffing setback during Tuesday’s meeting of the Committee on Health, Hospitals, and Human Services.

Employees had been hired based on an earlier completion timeline, he said, but the extended wait caused some to leave.

“Those individuals elected to move on. We are now re-recruiting for some critical positions to be back at the facility,” Dr. Smith told lawmakers.

Advertisement

Senator Avery Lewis said the update “wasn't really good news to me.”

The cancer institute, which closed after the 2017 hurricanes, had been expected to reopen in the second quarter of 2026. Unsuccessful solicitations for minor medical equipment, furniture, fixtures and information technology equipment disrupted that timeline.

Darryl Smalls, executive director of facilities and capital development for the Territorial Hospital Redevelopment Team, said procurement has since advanced.

Working with its medical equipment planner, the team has “successfully procured 100% of the 542 items that were included in the minor medical solicitations,” he told the committee.

The team has also entered into a contract for furniture, fixtures and equipment and expects to sign a separate contract for information technology equipment.

Equipment purchases exceed $6,992,259.84, Smalls said, with more than 1,000 items expected to arrive. He said deliveries would be tracked closely.

Major equipment, including the linear accelerator and CT simulator, is already inside the facility. However, additional components are needed before the equipment can be tested and certified.

“There are some key components that the physicist needs to certify the equipment,” Smalls told Lewis. Those components have been ordered and paid for, he said.

Smalls projected that after January 2027, “95 to 100 percent of the equipment that is required for the facility” would be on site.

The cancer center was one of several healthcare projects discussed during the hearing, with lawmakers receiving updates on construction, procurement problems and unresolved pricing.

On St. Croix, the interim hemodialysis facility is approximately 80 percent complete, Smalls said. Electrical wiring, plumbing, heating and air-conditioning installation, and interior drywall work remain underway.

He said construction remains on schedule for anticipated completion in January 2027. Solicitations for information technology, furniture, fixtures and minor medical equipment are expected to be advertised in December.

On St. John, the redevelopment team continues preconstruction work for the Myrah Keating Smith Community Health Center, with completion currently targeted for 2029.

To maintain water service to the interim facility during demolition and reconstruction, the team has facilitated construction of an enclosure for approximately 12,000 gallons of water storage while the existing cistern is demolished, Smalls said.

The Schneider Regional Medical Center rebuild also remains in preconstruction. Smalls told lawmakers that the project had been solicited multiple times and that the Public Finance Authority received responses to the latest solicitation days before Tuesday’s hearing. Evaluation would begin shortly, he said.

Senator Kurt Vialet questioned the failure that forced the procurement to restart. A September 22 PFA letter, previously obtained by the Consortium, stated that an evaluator had not followed established evaluation procedures, prompting cancellation and a new solicitation. The finding concerned the government’s evaluation process and did not attribute wrongdoing to previously selected contractor Suffolk Construction.

Smalls, who said he had participated in prior evaluation teams, told Vialet he had “heard that statement publicly” but could not provide further detail.

Vialet asked what consequences had followed for the evaluator responsible for the procedural failure.

“At some point, individuals are going to have to be penalized because we continue to get in problems with the fed because of not following procedures,” he said.

For the planned Juan F. Luis Hospital rebuild, Smalls said a contractor had been selected, but its pricing did not align with the government’s budget. The parties are undertaking an “optimization” process to reconcile the project with current construction costs.

“I believe that we are at a good spot right now, and we're moving forward to the next step,” Smalls told Vialet.

Advertisement

The updates come amid heightened federal scrutiny of the territory’s recovery program. ODR Director Adrienne Williams-Octalien told the Consortium that an OMB official threatened to withdraw funding during a recent meeting. Territorial officials are expected to present FEMA and OMB with a consolidated execution plan during the week of December 7. The warning did not itself cancel funding.